[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151068":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151068,803,1,"单选题","在可行性研究及以前阶段的勘测、规划设计等前期工作中的工程质量（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","由项目法人负责",false,{"key":16,"text":17,"correct":14},"B","由项目审批部门负责",{"key":19,"text":20,"correct":21},"C","由设计单位负责",true,{"key":23,"text":24,"correct":14},"D","由项目主管部门负责","2020版教材P243 \u002F 2019版教材P246 水力发电工程建设各方质量管理职责里的内容。根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），除可行性研究及以前阶段的勘测、规划设计等前期工作中的工程质量由设计单位负责，设计审查单位负审查责任。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]