[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151064":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151064,803,1,"单选题","工程主要材料、设备，应由（ ）负责招标采购。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程主管单位",false,{"key":16,"text":17,"correct":14},"B","建设行政主管部门",{"key":19,"text":20,"correct":21},"C","合同规定的采购单位",true,{"key":23,"text":24,"correct":14},"D","质量监督部门","2020版教材P244 \u002F 2019版教材P247 水力发电工程建设各方质量管理职责。根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），工程主要材料、设备，应由合同规定的采购单位负责招标采购，选定材料、设备的供货厂家，并负责材料、设备的检验、监造工作，对其质量负责；其他单位不得干预采购单位按规定进行自主采购的权利而指定供货厂家或产品。这里和水利工程中的细微不同之处：水利水电工程所需材料宜由承包人负责采购；主要工程设备（如闸门、启闭机、水泵、水轮机、电动机）可由发包人另行组织招标采购。而对于电气设备、清污机、起重机、电梯等设备可根据招标项目具体情况在专用合同条款中进一步约定。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]