[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151063":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151063,803,1,"单选题","施工单位在工程项目现场的行政负责人对本单位在工程建设中的质量工作负（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接领导责任",true,{"key":16,"text":17,"correct":18},"B","间接领导责任",false,{"key":20,"text":21,"correct":18},"C","技术责任",{"key":23,"text":24,"correct":18},"D","间接责任","2020版教材P244 \u002F 2019版教材P247 水力发电工程建设各方质量管理职责。根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），建设项目的项目法人、監理、设计、施工单位的行政正职，对本单位的质量工作负领导责任。各单位在工程项目现场的行政负责人对本单位在工程建设中的质量工作负直接领导责任。监理、设计、施工单位的工程项目技术负责人（总监、设总、总工）对质量工作负技术责任。具体工作人员为直接责任人。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]