[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151056":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151056,803,1,"单选题","工程设计方案发生重大变更时，必须由项目法人组织设计单位编制相应的设计文件，并由项目法人报（ ）审查批准。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","上级主管部门",false,{"key":16,"text":17,"correct":14},"B","有设计审批权的部门",{"key":19,"text":20,"correct":21},"C","原设计审批部门",true,{"key":23,"text":24,"correct":14},"D","有资质的咨询单位","2020版教材P245 \u002F 2019版教材P248 根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），有关设计质量管理的内容。工程规模、安全设防标准、枢纽总体布置、主要建筑物形式、施工期度汛标准及其他涉及工程安全的重大问题的设计原则、标准和方案发生重大变更时，必须由项目法人组织设计单位编制相应的设计文件，并由项目法人报原设计审批部门审查批准。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]