[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151054":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1151054,803,1,"单选题","对于设计单位不同意采纳的设计变更建议，（ ）有权作出一般设计变更的决策。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","监理单位",false,{"key":16,"text":17,"correct":18},"B","项目法人",true,{"key":20,"text":21,"correct":14},"C","设计审批部门",{"key":23,"text":24,"correct":14},"D","施工单位","2020版教材P245 \u002F 2019版教材P248 根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），有关设计质量管理的内容对于项目法人、监理、施工等单位和个人提出的一般设计变更建议，设计单位应认真听取并加以论证，积极采纳合理化建议，并对采纳建议所作的设计质量负责。对于设计单位不同意采纳的设计变更建议，项目法人有权作出一般设计变更的决策，并对决策方案的正确性负责，设计单位受项目法人委托进行变更设计时对自己所作的设计成果负责。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]