[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151053":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1151053,803,1,"单选题","施工单位的“三级检查制度”指（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","班组初检、作业队复检、项目部终检",true,{"key":16,"text":17,"correct":18},"B","班组初检、作业队复检、项目经理终检",false,{"key":20,"text":21,"correct":18},"C","检验员初检、作业队复检、项目部终检",{"key":23,"text":24,"correct":18},"D","班组初检、项目经理复检、项目部终检","2020版教材P246 \u002F 2019版教材P249 根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），有关施工质量管理的内容。单元工程的检查验收，施工单位应按“三级检查制度”（班组初检、作业队复检、项目部终检）的原则进行自检，在自检合格的基础上，由监理单位进行终检验收。经监理单位同意，施工单位的自检工作分级层次可以适当简化。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]