[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1151051":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1151051,803,1,"单选题","施工单位进行工程分包时，分包部分不宜超过合同工作量的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":14},"B","50%",{"key":19,"text":20,"correct":21},"C","30%",true,{"key":23,"text":24,"correct":14},"D","25%","2020版教材P246 \u002F 2019版教材P249 根据《水电建设工程质量管理暂行办法》（电水农[1997]220号），有关施工质量管理的内容。施工单位进行分包时，必须经监理单位同意并审查分包施工单位保证工程质量的能力，出具书面意见报项目法人批准。分包部分不宜超过合同工作量的30%。分包施工单位不得再次进行分包。项目法人不得违反合同和有关规定强令施工单位进行分包。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]