[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150993":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150993,803,1,"单选题","水利工程质量事故分类中，属于必要条件的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","直接经济损失的大小",true,{"key":16,"text":17,"correct":18},"B","事故处理需要的工期",false,{"key":20,"text":21,"correct":18},"C","是否影响使用功能",{"key":23,"text":24,"correct":18},"D","是否影响寿命","2020版教材P207 \u002F 2019版教材P210 注：1、直接经济损失费用为必要条件。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]