[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150985":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150985,803,1,"单选题","事故处理需要进行重大设计变更的，必须经（ ）审定后方可实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","原设计审批部门",true,{"key":16,"text":17,"correct":18},"B","原设计单位",false,{"key":20,"text":21,"correct":18},"C","上级设计审批部门",{"key":23,"text":24,"correct":18},"D","项目主管部门","2020版教材P209 \u002F 2019版教材P212 事故处理需要进行设计变更的，需原设计单位或有资质的单位提出设计变更方案，需要进行重大设计变更的，必须经原设计审批部门审定后实施。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]