[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150967":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150967,803,1,"单选题","根据《水利水电工程标准施工招标文件》，工程移交发包人后，保修期内的缺陷修复工作应由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":18},"B","承包人",true,{"key":20,"text":21,"correct":14},"C","监理人",{"key":23,"text":24,"correct":14},"D","质量监督机构","2020版教材P214 \u002F 2019版教材P217 （3）水利工程在规定的保修期内，出现工程质量问题，一般由原施工单位承担保修，所需费用由责任方承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]