[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150963":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150963,803,1,"单选题","未经（ ）签字之前，建筑材料、建筑构配件和设备不得在工程上使用或者安装，施工单位不得进行下一道工序的施工。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目经理",false,{"key":16,"text":17,"correct":14},"B","总监理工程师",{"key":19,"text":20,"correct":21},"C","监理人员",true,{"key":23,"text":24,"correct":14},"D","项目法人","2020版教材P214 \u002F 2019版教材P217 监理单位必须配备足够合格的监理人员，未经监理人员签字认可，建筑材料、构配件和设备不得在工程上使用或安装，不得进入下一道工序的施工，不得拨付工程进度款，不得进行竣工验收。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]