[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150960":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150960,803,1,"单选题","根据《水利水电工程标准施工招标文件》，发包人负责采购的工程设备，应由发包人和承包人按合同规定共同验收，在验收时，承包人应按监理人指示进行工程设备的检验测试，并将检验结果提交监理人，其所需费用由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","监理人",false,{"key":20,"text":21,"correct":18},"C","承包人",{"key":23,"text":24,"correct":18},"D","设备供应商","2020版教材P214 \u002F 2019版教材P217 在工程建设中，材料和设备无论是项目法人（建设单位）还是施工单位采购，根据《水利工程质量管理规定》（水利部令第7号），建筑材料和工程设备的质量由采购单位承担相应责任。因此由发包人负责采购的工程设备，其所需费用由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]