[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150953":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150953,803,1,"单选题","工程设计有重大修改的，项目法人（建设单位）报（ ）批准。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","原设计审批部门",true,{"key":16,"text":17,"correct":18},"B","所在地主管部门",false,{"key":20,"text":21,"correct":18},"C","上级主管部门",{"key":23,"text":24,"correct":18},"D","省级以上主管部门","2020版教材P216 \u002F 2019版教材P219 工程建设项目实施过程中，由于地质情况变化等原因对于已批准的设计进行局部修改是正常现象，也是设计单位的“在施工过程中要碎石掌握施工现场情况，优化设计，解决设计有关问题”的一项主要工作，但重大设计变更（修改）应报原设计审批部门批准，因为设计单位没有项目审批权。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]