[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150935":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150935,803,1,"单选题","根据《水利水电工程标准施工招标文件》，承包人有权根据本合同任何条款及其他有关规定，向发包人索取追加付款，但应在索赔事件发生后的（ ）内，将索赔意向书提交发包人和监理人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","28天",true,{"key":16,"text":17,"correct":18},"B","42天",false,{"key":20,"text":21,"correct":18},"C","56天",{"key":23,"text":24,"correct":18},"D","半年","2020版教材P205 \u002F 2019版教材P208 （1）7承包人应在知道或应当知道索赔事件发生后28天内，向监理人递交索赔意向通知书，并说明发生索赔事件的事由。承包人未在前述28天内发出索赔意向通知书的，丧失要求追加付款和（或）延长工期的权利。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]