[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150934":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150934,803,1,"单选题","根据《水利水电工程标准施工招标文件》，发包人收到监理人签证的月进度付款证书并审批后支付给承包人，支付时间不应超过监理人收到月进度付款申请单后（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":14},"B","14",{"key":19,"text":20,"correct":14},"C","21",{"key":22,"text":23,"correct":24},"D","28",true,"2020版教材P203 \u002F 2019版教材P206 （2）发包人应在监理人收到进度付款申请单后的28天内，将进度应付款支付给承包人。发包人不按期支付的，按专用合同条款的约定支付逾期付款违约金。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]