[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150933":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150933,803,1,"单选题","某大型泵站工程进行主泵房底板土方开挖，其相关资料见下表，则最终发包人应向承包人支付的主泵房底板土方开挖的价款应为（ ）万元。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","112",false,{"key":16,"text":17,"correct":18},"B","108",true,{"key":20,"text":21,"correct":14},"C","114",{"key":23,"text":24,"correct":14},"D","220","2020版教材P201 \u002F 2019版教材P204 已标价工程量清单中的单价子目工程量为估算工程量，结算工程量是承包人实际完后的，并按合同约定的计量方法进行计量的工程量。因此，10×10.8=108万元。 @##",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]