[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150928":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150928,803,1,"单选题","根据《水利水电工程标准施工招标文件》，由于不可抗力的自然或社会因素引起的暂停施工应属于（ ）的责任。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","承包人",false,{"key":20,"text":21,"correct":18},"C","设计单位",{"key":23,"text":24,"correct":18},"D","监理人","2020版教材P198 \u002F 2019版教材P201 属于下列任何一种情况引起的暂停施工，均为发包人的责任：（1）由于发包人违约引起的暂停施工。（2）由于不可抗力的自然或社会因素引起的暂停施工。（3）专用合同条款中约定的其他由于发包人原因引起的暂停施工。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]