[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150926":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150926,803,1,"单选题","某大型泵站施工过程中，由于主泵房施工的需要，在征得监理单位批准后，施工单位进行了补充地质勘探，由此产生的费用应由（ ）承担。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人",true,{"key":16,"text":17,"correct":18},"B","监理人",false,{"key":20,"text":21,"correct":18},"C","承包人",{"key":23,"text":24,"correct":18},"D","该泵站工程的原勘测单位","2020版教材P196 \u002F 2019版教材P199 在合同实施期间’监理人可以指示承包人进行必要的补充地质勘探并提供有关资料。承包人为本合同永久工程施工的需要进行钋充地质勘探时，须经监理人批准，并应向监理人提交有关资料，上述补充勘探的费用由发包人承担",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]