[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150924":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150924,803,1,"单选题","根据《水利水电工程标准施工招标文件》，承包人负责采购的材料和工程设备，应由承包人会同监理人进行检验和交货验收，并应进行材料的抽样检验和工程设备的检验测试，其所需费用由（ ）承担。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":21},"C","承包人",true,{"key":23,"text":24,"correct":14},"D","材料和设备供应商","2020版教材P195 \u002F 2019版教材P198 对承包人提供的材料和工程设备，承包人应会同监理人进行检验和交货验收，查验材料合格证明和产品合格证书，并按合同约定和监理人指示，进行材料的抽样检验和工程设备的检验测试，检验和测试结果应提交监理人，所需费用由承包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]