[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150922":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150922,803,1,"单选题","根据《水利水电工程标准施丁招标文件》，除专用合同条款另有约定外，现场测量基本控制点、基线和水准点应由（ ）提供。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人",false,{"key":16,"text":17,"correct":18},"B","发包人",true,{"key":20,"text":21,"correct":14},"C","监理人",{"key":23,"text":24,"correct":14},"D","质量监督机构","2020版教材P195 \u002F 2019版教材P198 发包人应在本合同协议书签订后的14天内，向承包人提供测量基准点、基准线和水准点及其相关资料。发包人应对其提供的测量基准点、基准线和水准点及其书面资料的真实性、准确性和完整性负责。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]