[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150898":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150898,803,1,"单选题","水利工程施工项目的招标中，开标时间与投标截止时间的关系是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","开标时间早于投标截止时间",false,{"key":16,"text":17,"correct":14},"B","开标时间晚于投标截止时间",{"key":19,"text":20,"correct":21},"C","开标时间等于投标截止时间",true,{"key":23,"text":24,"correct":14},"D","没关系","2020版教材P178 \u002F 2019版教材P181 自招标文件开始发出之日起至投标人提交投标文件截止，最短不得少于20日；投标截止时间与开标时间应当为同一时间。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]