[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150887":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150887,803,1,"单选题","下列关于标底和最高投标限价的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","一个招标项目只能有一个标底",false,{"key":16,"text":17,"correct":14},"B","招标项目设有标底的，招标人应当在开标时公布",{"key":19,"text":20,"correct":21},"C","招标人可以规定最低投标限价",true,{"key":23,"text":24,"correct":14},"D","招标人可以规定最高投标限价","2020版教材P177 \u002F 2019版教材P180 招标人设有最高投标限价的，应当在招标文件中明确最高投标限价或者最高投标限价的计算方法；招标人不得规定最低投标限价；投标最高限价可以是一个总价，也可以是总价及构成总价的主要分项价。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]