[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150882":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150882,803,1,"单选题","分包单位必须对其分包工程的施工质量向（ ）负责。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","质量监督机构",false,{"key":16,"text":17,"correct":14},"B","项目法人",{"key":19,"text":20,"correct":14},"C","监理单位",{"key":22,"text":23,"correct":24},"D","总包单位",true,"2020版教材P175 \u002F 2019版教材P178 分包人应当按照分包合同的约定对其分包的工程向承包人负责，分包人应接受承包人对分包项目所进行的工程进度、质量、安全、计量和验收的监督和管理。承包人和分包人就分包项目对发包人承担连带责任。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]