[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150878":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150878,803,1,"单选题","关于项目法人指定分包，违反规定的说法是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","特殊情况下（如应急防汛等），项目法人可直接指定分包人",false,{"key":16,"text":17,"correct":14},"B","因非承包人原因形成指定分包条件的，项目法人的指定分包不得增加承包人的额外费用",{"key":19,"text":20,"correct":14},"C","因承包人原因形成指定分包条件的，承包人应负责因指定分包增加的相应费用",{"key":22,"text":23,"correct":24},"D","指定分包时，不得增加承包单位的额外费用",true,"2020版教材P173 \u002F 2019版教材P175 《水利建没工程施工分包管理规定》对项目法人分包管理职责。因非承包人原因形成指定分包条件的，项目法人的指定分包不得增加承包人的额外费用；因承包人原因形成指定分包条件的，承包人应负责因指定分包增加的相应费用。D选项，要分清楚是谁的原因。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]