[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150873":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150873,803,1,"单选题","根据《水利建设工程施工分包管理规定》（水建管[2005]304号），分包合同必须遵循（ ）合同中的技术、经济条款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包合同的各项原则，满足承包",true,{"key":16,"text":17,"correct":18},"B","承包合同的各项原则，满足分包",false,{"key":20,"text":21,"correct":18},"C","分包合同的各项原则，满足分包",{"key":23,"text":24,"correct":18},"D","分包合同的各项原则，满足承包","2020版教材P174 \u002F 2019版教材P176 根据《水利建设工程施丁分包管理规定》，承包单位分包的管理职责。承包人和分包人应当依法签订分包合同，并履行合同约定的义务。分包合同必须遵循承包合同的各项原则，满足承包合同中技术、经济条款。承包人应在分包合同签订后7个工作日内，送发包人备案。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]