[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150860":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150860,803,1,"单选题","竣工决算应包括项目（ ）的全部费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","从施工到竣工验收",false,{"key":16,"text":17,"correct":14},"B","从主体工程施工到竣工验收",{"key":19,"text":20,"correct":21},"C","从筹建到竣工验收",true,{"key":23,"text":24,"correct":14},"D","从筹建到试运行","2020版教材P168 \u002F 2019版教材P170 竣工财务决算应反映项目从筹建到竣工验收的全部费用。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]