[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150844":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150844,803,1,"单选题","根据水利部《水利工程设计变更管理暂行办法》，设计变更是指自水利工程初步设计批准之日起至工程竣工验收交付使用之日止，对已批准的（ ）所进行的修改活动。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目建议书",false,{"key":16,"text":17,"correct":14},"B","可行性研究",{"key":19,"text":20,"correct":21},"C","初步设计",true,{"key":23,"text":24,"correct":14},"D","施工图","2020版教材P150 \u002F 2019版教材P152 根据水利部《水利工程设计变更管理暂行办法》（水规计[2012]93号），设计变更需注意以下要求：设计变更是指自水利工程初步设计批准之日起至工程竣工验收交付使用之日止，对已批准的初步设计所进行的修改活动。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]