[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150841":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150841,803,1,"单选题","对项目的立项、勘察设计、施工、建设管理、生产（运行）等进行的评价称为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","影响评价",false,{"key":16,"text":17,"correct":14},"B","经济效益评价",{"key":19,"text":20,"correct":21},"C","过程评价",true,{"key":23,"text":24,"correct":14},"D","建设评价","2020版教材P148 \u002F 2019版教材P150 根据《水利工程建设项目管理规定（试行）》（水建[1995]128号），水利工程建设程序后评价各阶段中的过程评价。过程评价—前期工作、建设实施、运行管理等。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]