[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150834":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150834,803,1,"单选题","水利工程建设前期工作一般分为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可行性研究报告",false,{"key":16,"text":17,"correct":14},"B","可行性研究报告、初步设计",{"key":19,"text":20,"correct":14},"C","项目建议书、可行性研究报告",{"key":22,"text":23,"correct":24},"D","项目建议书、可行性研究报告和初步设计",true,"2020版教材P146 \u002F 2019版教材P148 水利工程建设程序中的前期工作有几项组成。一般情况下，项目建议书、可行性研究报告、初步设计称为前期工作。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]