[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150832":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150832,803,1,"单选题","按《水利工程建设程序管理暂行规定》的要求，水利工程建设程序的最后一个阶段为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","竣工验收",false,{"key":16,"text":17,"correct":14},"B","生产准备",{"key":19,"text":20,"correct":14},"C","生产运行",{"key":22,"text":23,"correct":24},"D","项目后评价",true,"2020版教材P145 \u002F 2019版教材P147 根据水利部《水利工程建设项目管理规定（试行）》（水建[1995]128号）和有关::规定，水利工程建设项目的实施，必须执行工程建设程序。水利工程建设程序一般分为：项目建议书、可行性研究报告、施工准备、初步设计、建设实施、生产准备、竣工验收、后评价等阶段。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]