[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150824":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150824,803,1,"单选题","帷幕灌浆全孔灌浆结束后，封孔灌浆时间宜为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20min",false,{"key":16,"text":17,"correct":14},"B","30min",{"key":19,"text":20,"correct":14},"C","40min",{"key":22,"text":23,"correct":24},"D","1h",true,"2020\u002F2019教材P66 全孔灌浆结束后，应以水胶比为0.5的新鲜普通水泥浆液置换孔内稀浆或积水，采用全孔灌浆封孔法封孔。封孔灌浆压.力:采周自上而下分段灌浆法和自下而上分段灌浆法时可采用全孔段平均灌浆压力或2MPa;采用孔口封闭法时，可采用该孔最大灌浆压力。封孔灌浆时间可为1h。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]