[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150822":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150822,803,1,"单选题","帷幕灌浆施工中，采用自下而上分段灌浆法时，先导孔应（ ）进行压水试验。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","自下而上分段",false,{"key":16,"text":17,"correct":14},"B","自下而上全段",{"key":19,"text":20,"correct":21},"C","自上而下分段",true,{"key":23,"text":24,"correct":14},"D","自上而下全段","2020\u002F2019教材P64 帷幕灌浆先导孔、质量检査孔应自上而下分段进行压水试验，压水试验宜采用单点法。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]