[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150761":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150761,803,1,"单选题","疏浚工程施工中，监理单位平行检验测量点数不应少于施工单位检测点数的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3%",false,{"key":16,"text":17,"correct":18},"B","5%",true,{"key":20,"text":21,"correct":14},"C","8%",{"key":23,"text":24,"correct":14},"D","10%","2020版教材P121 \u002F 2019版教材P123 监理单位复核检验测量点数:平行检测不应少于施工单位检测点数5%;跟踪检测不应少于施工单位检测点数10%。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]