[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150760":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150760,803,1,"单选题","疏浚工程完工后，项目法人应提出验收申请，验收主持单位应在工程完工（ ）日内及时组织验收。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","21",{"key":23,"text":24,"correct":14},"D","28","2020版教材P121 \u002F 2019版教材P123 工程完工后，项目法人应提出验收申请，验收主持单位应在工程完工14日内及时组织验收。工程完工验收后，项0法人应与施工单位在30个工作日内专人负责工程的交接工作，交接过程应有完整的文字记录,双方交接负责人签字。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]