[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150739":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150739,803,1,"单选题","在软土堤基上筑堤时，如堤身两侧设有压载平面，两者的填筑顺序为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","先筑堤身后压载",false,{"key":16,"text":17,"correct":14},"B","先筑压载后堤身",{"key":19,"text":20,"correct":21},"C","两者同步填筑",true,{"key":23,"text":24,"correct":14},"D","无所谓","2020版教材P117 \u002F 2019版教材P119 （4）在软土堤基上筑堤时，如堤身两侧设有压载平台，两者应按设计断面同步分层填筑，严禁先筑堤身后压载。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]