[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150737,803,1,"单选题","下列关于堤防填筑作业的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","地面起伏不平时，应顺坡填筑",true,{"key":16,"text":17,"correct":18},"B","堤身两侧设有压载平台，两者应按设计断面同步分层填筑",false,{"key":20,"text":21,"correct":18},"C","相邻施工段的作业面宜均衡上升，段间出现高差，应以斜坡面相接",{"key":23,"text":24,"correct":18},"D","光面碾压的黏性土填料层，在新层铺料前，应作刨毛处理","2020版教材P117 \u002F 2019版教材P119 （1）地面起伏不平时，应按水平彡层由低处开始逐层填筑，不得顺坡铺填；堤防横断面上的地面坡度陡于1:5时，应将地面坡度削至缓于1:5。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]