[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150732":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150732,803,1,"单选题","碾压混凝土坝的施工工艺程序一般为入仓、平仓、（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","切缝、振动碾压、无振碾压",false,{"key":16,"text":17,"correct":18},"B","振动碾压、切缝、无振碾压",true,{"key":20,"text":21,"correct":14},"C","无振碾压、切缝、振动碾压",{"key":23,"text":24,"correct":14},"D","振动碾压、无振碾压、切缝","2020版教材P114 \u002F 2019版教材P116 碾压混凝土坝的施工工艺程序是先在初浇层铺砂浆，汽车运输人仓，平仓机平仓，振动压实机压实，振动切缝机切缝，切完缝再沿缝无振碾压两遍。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]