[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150717":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150717,803,1,"单选题","在施工中混凝土块体大小必须与混凝土制备、运输和浇筑的生产能力相适应，主要是为了避免（ ）出现。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","冷缝",true,{"key":16,"text":17,"correct":18},"B","水平缝",false,{"key":20,"text":21,"correct":18},"C","临时缝",{"key":23,"text":24,"correct":18},"D","错缝","2020版教材P112 \u002F 2019版教材P114 （3）在施工中为了避免冷缝，块体大小必须与混凝土制备、运输和浇筑的生产能力相适应，即要保证在混凝土初凝时间内所浇的混凝土方量，必须等于或大于块体的一个浇筑层的混凝土方量。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]