[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150694":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150694,803,1,"单选题","混凝土面板垂直缝砂浆条铺设的施工程序正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先铺止水，再铺砂浆，架立侧模",false,{"key":16,"text":17,"correct":18},"B","先铺砂浆，再铺止水，架立侧模",true,{"key":20,"text":21,"correct":14},"C","架立侧模，再铺止水，铺砂浆",{"key":23,"text":24,"correct":14},"D","架立侧模，再铺砂浆，铺止水","2020版教材P91 \u002F 2019版教材P93 砂浆铺设完成后，再在其上铺设止水，架立侧模。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]