[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150680":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150680,803,1,"单选题","在碾压土石坝坝体填筑中，各分段之间的接坡坡比一般应缓于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1：3",true,{"key":16,"text":17,"correct":18},"B","1：2",false,{"key":20,"text":21,"correct":18},"C","1：2.5",{"key":23,"text":24,"correct":18},"D","1：1","2020版教材P85 \u002F 2019版教材P88 在坝体填筑中，层与层之间分段接头应错开一定距离，同时分段条带应与坝轴线平行布置，各分段之间不应形成过大的高差。接坡坡比一般缓于1:3",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]