[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150577":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150577,803,1,"单选题","根据山区、丘陵地区永久性水工建筑物洪水标准要求，对一级混凝土坝，在校核情况下的洪水重现期为( )年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10000～5000",false,{"key":16,"text":17,"correct":18},"B","5000～2000",true,{"key":20,"text":21,"correct":14},"C","5000～1000",{"key":23,"text":24,"correct":14},"D","2000～1000","2020\u002F2019教材P17 水库及水电站工程永久性水工建筑物山区、丘陵区水库工程永久性水工建筑物的洪水标准。山E 、丘陵区水库工程永久性水工建筑物的洪水标准[重现期（年）] 表1F411021-6。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]