[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150574":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1150574,803,1,"单选题","根据《水利水电工程等级划分及洪水标准》SL252-2017，某土石坝施工中，汛前达到拦洪度汛高程（超过围堰顶高程），相应库容为5000万m3，坝体施工期临时度汛的洪水标准为()年。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","20～10",false,{"key":16,"text":17,"correct":14},"B","50～20",{"key":19,"text":20,"correct":21},"C","100～50",true,{"key":23,"text":24,"correct":14},"D","≥100","2020\u002F2019教材P17 当水库大坝施工高程超过临时性挡水建筑物顶部高程时，坝体施工期临时度汛的洪水标准。本题为课本改版后根据新规增加的内容，必须重视。根据水库大坝施工期洪水标准表[重现期（年）]表1F411021-8。大坝级别为3级，土石坝，",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]