[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150567":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150567,803,1,"单选题","某堤防工程，其保护对象的防洪标准为50年，该堤防工程级别为()级。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","2020\u002F2019教材P15 堤防工程的级别。防洪工程中堤防永久性水工建筑物的级别应根据其保护对象的防洪标准按表1F411021-4确定。当经批准的流域、区域防洪规划另有规定时，应按其规定执行。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]