[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150565":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1150565,803,1,"单选题","填筑工程量测算时，独立两次对同一工程量测算体积之差，在小于该体积的()时，可取中数作为最后值。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3%",true,{"key":16,"text":17,"correct":18},"B","4%",false,{"key":20,"text":21,"correct":18},"C","5%",{"key":23,"text":24,"correct":18},"D","6%","2020\u002F2019教材P9 填筑工程量测算：两次独立测量同一工程，其测算体积之较差，在小于该体积的3%时，可取中数作为最后值。这里区分开挖工程量的测算中断面测量和工程量计算：两次独立测量同一区域的开挖工程量其差值小于5% ( 岩石）和7% ( 土方）时，可取中数作为最后值。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]