[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150514":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150514,803,1,"单选题","根据合同技术条款计量与支付规则，超大件超过合同约定的限度时，增加的费用由（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","承包人承担",false,{"key":16,"text":17,"correct":18},"B","发包人承担",true,{"key":20,"text":21,"correct":14},"C","监理人确定承担者",{"key":23,"text":24,"correct":14},"D","争议调解组确定承担者","本题考查的是施工阶段成本管理。超大、超重件的尺寸或重量超出合同约定的限度时，增加的费用由发包人承担。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]