[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150507":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150507,803,1,"单选题","以下情形可以采取不平衡报价的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工程要求急的工程",false,{"key":16,"text":17,"correct":14},"B","投标竞争对手多的工程",{"key":19,"text":20,"correct":14},"C","风险较大的特殊工程",{"key":22,"text":23,"correct":24},"D","招标图纸不明确，预估工程量可能增加的",true,"A、C：高报；B：低报。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]