[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150506":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150506,803,1,"单选题","以下清单中，只报单价，不计入投标总价中的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分类分项工程量清单",false,{"key":16,"text":17,"correct":18},"B","零星项目清单",true,{"key":20,"text":21,"correct":14},"C","其他项目清单",{"key":23,"text":24,"correct":14},"D","措施项目清单","零星项目清单只报单价，不计入投标总价。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]