[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150504":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150504,803,1,"单选题","在工程进度曲线中，通过实际进度与计划进度进行比较，下列（ ）难以通过比较得知。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","实际工程进展速度",false,{"key":16,"text":17,"correct":14},"B","进度超前或拖延的时间",{"key":19,"text":20,"correct":14},"C","工程的完成情况",{"key":22,"text":23,"correct":24},"D","施工质量的达标情况",true,"本题考查的是水利水电工程施工进度计划。通过比较可以获得如下信息：（1）实际工程进展速度；（2）进度超前或拖延的时间；（3）工程量的完成情况；（4）后续工程进度预测 。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]