[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150502":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1150502,803,1,"单选题","下列属于超过一定规模的危险性较大的单项工程的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","集中线荷载15～20kN\u002Fm的混凝土模板支撑工程",false,{"key":16,"text":17,"correct":18},"B","搭设高度9m的混凝土模板支撑工程",true,{"key":20,"text":21,"correct":14},"C","开挖深度2.3m的土石方开挖工程",{"key":23,"text":24,"correct":14},"D","围堰工程","本题考查的是水利水电工程专项施工方案。搭设高度8m及以上的混凝土模板支撑工程即属于超过一定规模的危险性较大的单项工程。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]