[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1150500":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1150500,803,1,"单选题","横道图作为建设工程进度计划的直观表示方法，其主要优点是能够（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","明确表达工作之间的逻辑关系",false,{"key":16,"text":17,"correct":14},"B","直观表示工作所拥有的机动时间",{"key":19,"text":20,"correct":14},"C","明确表达影响工期的关键工作",{"key":22,"text":23,"correct":24},"D","直观表示各项工作的开始和结束时间",true,"本题考查的是水利水电工程施工进度计划。横道图计划明确表示出各项工作的划分、工作的开始时间和完成时间、工作的持续时间、工作之间的相互搭接关系，以及整个工程项目的开工时间、完工时间等。",{"id":6,"name":27,"category":28,"favorite":29},"一建水利水电工程实务","建筑工程",0]